DOWNLOAD DATA

Environment

Site rehabilitation and restoration

Rehabilitation at AGL Macquarie was in line with the approved Rehabilitation Management Plan for Ravensworth and the draft Rehabilitation Management Plan for Liddell Ash Dam. Camden Gas Project wells continue to be progressively decommissioned and sites rehabilitated alongside continued production from remaining wells for AGL gas customers.

Site

Activity

FY23

AGL Macquarie

Total area of ongoing capping and rehabilitation of Liddell Ash Dam and Ravensworth mine

Liddell Ash Dam - 23.5 ha dust capped and revegetated for FY23
Ravensworth: 12.1 ha

AGL Loy Yang

Total operational footprint

1148.08 ha

Progressive rehabilitation over FY23

12.58ha

Cumulative total of rehabilitation since mining commenced

755.35 ha

Camden Gas Project

Number of the 144 well sites that have been, or are in the process of being, decommissioned, rehabilitated and returned to the respective landowner

117

PREVIOUS PAGEWaste

NEXT PAGEBusiness Intelligence